Office Move Checklist for Facilities Managers

hero fm 1272
The short version
  • Start planning an office move six to twelve months out. Lease notice periods and fit-out lead times set the real deadline.
  • Size the new space from attendance data, not headcount, or you will pay for desks nobody uses.
  • Rebuild desks, rooms and floor plans in your booking system before day one, so people can book the new office on the first morning.
  • Run a snag list for the first two weeks and keep one owner for every open issue.

An office move touches everything: the lease, IT, furniture, security, suppliers and every person who works there. Most problems come from things nobody owned, not from things that were hard. A shared checklist with a named owner for each line fixes most of that.

This office move checklist is written for facilities, workplace and HR teams. Use it as a timeline, copy the tables into your own tracker, and give every row an owner and a date.

6 to 12 months before the move

TaskWhy it matters
Check your lease end date, notice period and any break clauseSets the latest date you can give notice and the date you must be out
Name a move lead and a small project teamOne person accountable, with IT, HR, finance and facilities represented
Set the budget, including fit-out, furniture, IT, removals and overlap rentOverlap months and dilapidations are the costs most often missed
Pull attendance and booking data for at least a quarterShows how many desks and rooms you really need on the busiest normal day
Agree the brief for the new space: desks, rooms, quiet space, parkingTurns data into a requirement agents and landlords can quote against
Shortlist and view buildingsCheck transport, access, lifts, parking and hours, not just the floor area

For sizing, the office space calculator turns peak attendance into a desk and room count. The office space planning checklist covers the wider requirement.

3 to 6 months before the move

TaskWhy it matters
Sign the new lease and give notice on the old oneLocks in dates for everything that follows
Appoint fit-out, furniture and removals suppliersLead times for furniture and fit-out are often longer than expected
Agree the new layout and a stack planDecides which teams sit on which floor and in which neighbourhood
Book IT: internet lines, Wi-Fi survey, network, AV and phonesNew lines can take months to install
Plan access control, alarms and CCTVPeople need working passes on day one
Start a staff communication planEarly, regular updates reduce rumours and questions

1 to 3 months before the move

TaskWhy it matters
Tell customers, suppliers, banks and insurers the new addressPost, deliveries and invoices keep flowing
Update the address on your website, email signatures and legal registrationsAvoids visitors and couriers going to the old office
Build the new floor plans in your desk and room booking systemStaff can see and book the new office before they arrive
Name and label desks and meeting roomsRoom names and codes should match the signs on the doors
Plan the clear-out: archive, shred, recycle or sellMoving things you will throw away costs money
Update fire safety, first aid and evacuation plans for the new siteRequired before people work in the building
Name rooms once, in both places. Use the same room names and codes on the door signs and in the booking system. Our guide to conference room names has a simple naming system and 150+ ideas.

2 to 4 weeks before the move

TaskWhy it matters
Send each team its move-day instructions and new seatingPeople know where to go and what to pack
Issue packing crates and labels by team and deskLabels that match the floor plan speed up unpacking
Test IT, Wi-Fi, printers and meeting room AV in the new officeProblems found before the move do not stop work after it
Register visitors and deliveries for the new addressReception knows who is arriving from the first day
Confirm parking and building access for every personAvoids a queue at the door on day one

Move week and the first day

TaskWhy it matters
Back up data and shut down equipment in orderProtects files and speeds up reconnection
Have a person on site at both officesSomeone can answer the removal team’s questions at each end
Open desk and room bookings for the new officePeople book a desk before they travel in
Walk the building for safety and signageChecks fire exits, first aid kits and wayfinding
Run a welcome and a short tourHelps people find kitchens, rooms and quiet space fast

After the move

TaskWhy it matters
Keep a snag list for two weeks, with one owner per itemSmall faults get fixed instead of ignored
Hand back the old office to the lease termsProtects your deposit and limits dilapidation costs
Cancel old utilities, contracts and redirect postStops paying for a building you have left
Review desk and room use after the first monthShows whether the layout matches how people actually use it
Ask staff what works and what does notQuick fixes early build trust in the new space

Common office move mistakes

  • Sizing for headcount instead of attendance. In a hybrid office, not everyone is in on the same day. Measure the busiest normal day first.
  • Leaving IT too late. Internet lines and network work have long lead times. Book them as soon as the lease is signed.
  • No single owner. Every line on the checklist needs one name next to it.
  • Forgetting the booking system. If the new floor plan is not ready, day one becomes a desk scramble. The new office setup checklist covers desks, rooms, visitors and parking for the first morning.
  • Stopping at move day. The first month shows what needs to change. Plan time for it.

For larger programmes with many moves a year, see move management and moves, adds and changes.

Making the move easier with HybridHero

HybridHero helps before and after the move. Booking and check-in data from your current office shows how much space you really use, and analytics breaks it down by day, team and location. For the new office, you set up interactive floor plans, team neighbourhoods and meeting room booking before day one, and visitor management handles guests at the new reception.

Common questions

How far in advance should you plan an office move?

Six to twelve months for most offices. Your lease notice period and the lead times for fit-out, furniture and internet lines usually set the real deadline.

Who should manage an office move?

One named move lead, usually from facilities, operations or the office manager role, supported by IT, HR and finance. The lead owns the checklist and chases every open item.

How do you tell employees about an office move?

Early and often. Share the reason, the date and the new location as soon as the lease is signed, then send practical details closer to the move: seating, travel, parking, packing and day-one instructions.

What is often forgotten in an office move?

Address changes with suppliers and registrations, redirecting post, updating evacuation plans, and setting up the booking system for the new office. Put all of them on the checklist with an owner.